Quick Reference
Menu map, demo-data codes and statuses
Menu Map
| Group | Models |
|---|---|
| Compliance Overview | Exploration Project, Tenement, Compliance Snapshot |
| Obligations | Statutory Obligation, Obligation Action, Work Programme Commitment, Expenditure Obligation, Eligible Expenditure, Licence Condition |
| Approvals & Access | Approval Permit, Land Access Agreement, Tenement Party |
| Reporting | Statutory Submission, Submission Requirement, Regulator Correspondence, Evidence Item, Obligation Evidence |
| Licence Changes | Variation Application, Exemption Application, Renewal, Relinquishment |
| Assurance & Reference | Compliance Risk, Decision, Jurisdiction |
Key Codes in the Demo Data
The demo runs one project — Copperfield (PRJ-CF), a copper-gold exploration
project operated by Meridian Exploration Ltd in Western Australia (AU-WA,
DEMIRS) — carrying two tenements at two tenure stages so the chain is visible
end to end for a live licence while a second sits at application. Overall
compliance is AtRisk, driven by a single thread: the year-3 expenditure
shortfall. Same Copperfield project/tenement as the other two suite apps.
| Code | What it is |
|---|---|
AU-WA |
Jurisdiction — Western Australia, regulator DEMIRS, Mining Act 1978 (WA); TENGRAPH tenure + WAMEX reporting portals |
PRJ-CF |
The project — Copperfield, copper-gold, operator Meridian Exploration Ltd, compliance manager R. Adeyemi, overall status AtRisk |
E29/1234 |
Copperfield East — the live licence. Granted, 88 km², 250k min. annual expenditure, AtRisk. Carries the whole chain |
E29/1299 |
Copperfield West — Application pending grant, 54 km², UnderReview. The second tenure stage |
Holder / TraditionalOwner |
Tenement parties: Meridian Exploration (100% Holder) and Goldfields Land Aboriginal Corporation (TraditionalOwner) |
OBL-EXP-Y3 |
Year-3 minimum expenditure obligation — Material, AtRisk, High risk. The spine of the demo |
OBL-REP-Y2 |
Annual technical + expenditure report (Form 5) obligation — Material, Submitted, Moderate risk |
ACT-EXP-01 / -02 |
Obligation actions: forecast the spend gap (Complete, ~40k gap found) and prepare the exemption (InProgress) |
WPC-Y3-DRILL |
Year-3 drilling commitment — 2500 m committed, 1050 m actual, −1450 m variance, AtRisk |
WPC-Y3-GEOP |
Year-3 geophysics commitment — 100 line-km committed, 0 done, NotStarted |
EXPO-Y3 |
The expenditure obligation — 250k required, 210k eligible actual, 230k forecast, 20k shortfall, AtRisk |
YDS-2026-118 / PAL-5521 |
Eligible-expenditure line items — 180k eligible drilling (reviewed) and 30k assays (unreviewed) |
LC-ENV-01 / LC-HER-01 |
Licence conditions — drill-site rehabilitation (Compliant) and pre-disturbance heritage survey (Active) |
PMT-PoW-01 |
Programme of Work (drilling) 2026 — DEMIRS, Approved, rehab bond lodged |
PMT-ENV-02 |
Native Vegetation Clearing Permit — DWER, Submitted (awaiting approval) |
LAA-01 |
Land-access agreement — Copperfield Station pastoral lease, Active, whole of E29/1234 |
SUB-AR-Y2 |
The annual report submission — Form 5, QueryRaised (regulator queried apportionment) |
REQ-01 / REQ-02 |
Submission requirements — expenditure statement (Warning, queried) and technical report (Pass) |
CORR-01 / CORR-02 |
Regulator correspondence — Inbound query on apportionment (Sent) and Outbound methodology response (Closed) |
VAR-01 |
Work-programme variation — defer 1450 m of drilling into year 4, Submitted |
EXM-01 |
Expenditure exemption — partial relief for the 20k year-3 shortfall, Draft |
REN-01 |
Renewal — 5-year term planned against the 2028 renewal due-date, 44 km² relinquishment required, Planned |
REL-01 |
Relinquishment — statutory 50% (44 km²) handback at first renewal, Planned |
CR-01 |
The expenditure shortfall risk — Expenditure, likelihood 4 × consequence 3, residual High, Mitigating |
CR-02 |
The annual-report query risk — Reporting, residual Moderate, trend Improving, Monitoring |
EVD-01 / EVD-02 |
Evidence items — drilling invoice (Receipt) and approved PoW (Approval), each linked to an obligation |
DEC-EL-01 / -02 |
Decisions — apply to vary the work programme (Vary) and prepare a partial expenditure exemption (Exempt) |
| Compliance snapshot | 2026-08-31: 2 obligations open, 1 at risk, 0 overdue, 84% expenditure coverage, 1 high/critical risk, AtRisk |
The Year-3 Shortfall Thread, Step by Step
The one worked example that ties the whole app together — an expenditure shortfall becoming an exemption.
- Year 3 opens — obligation
OBL-EXP-Y3requires the 250k minimum annual expenditure onE29/1234; expenditure obligationEXPO-Y3tracks it. - Drilling runs behind — commitment
WPC-Y3-DRILLdelivers 1050 m of the committed 2500 m; ground-condition delays and an assay backlog are the cause. - Finance forecasts the gap — action
ACT-EXP-01projects eligible spend at ~230k against the 250k minimum: a ~20k shortfall. - A risk is raised —
CR-01,Expenditure, likelihood 4 × consequence 3, residualHigh, statusMitigating— thelicence.obligation.at_risksignal. - Two decisions are recorded —
DEC-EL-01to vary the work programme,DEC-EL-02to lodge a partial exemption, each with its legal basis on file. - A variation is submitted —
VAR-01defers 1450 m of drilling into year 4. - An exemption is drafted —
EXM-01seeks 20k of partial relief for the shortfall, evidenced byEXPO-Y3, stillDraft. - The snapshot surfaces it — the compliance snapshot reads
AtRisk, 84% expenditure coverage, one high/critical risk. The project's overall status follows the shortfall to the top.
Status Vocabularies (the important ones)
Compliance status (project / tenement / snapshot): OnTrack · AtRisk ·
NonCompliant · UnderReview
Licence status (Tenement): Application · Granted · RenewalPending ·
Suspended · Expired · Relinquished · Cancelled
Obligation status (StatutoryObligation): NotDue · Planned · InProgress ·
AtRisk · Overdue · Submitted · Accepted · Rejected · Waived · Closed
Obligation type: Expenditure · WorkProgramme · AnnualReport · TechnicalReport
· Environment · LandAccess · Community · Renewal · Rent · Fee · Relinquishment ·
DataSubmission · Other
Materiality (obligations, decisions): Routine · Important · Material
Obligation-action status: NotStarted · InProgress · Blocked · Complete ·
Cancelled
Work-programme commitment status: NotStarted · OnTrack · AtRisk · Complete ·
Shortfall · Varied · Waived
Expenditure-obligation status: NotDue · OnTrack · AtRisk · Shortfall · Met ·
ExemptionApplied · Accepted
Licence-condition status: Active · AtRisk · Compliant · NonCompliant ·
Expired · Waived
Permit status (ApprovalPermit): Required · Preparing · Submitted · Approved
· Conditional · Rejected · Expired · NotRequired
Land-access status: Negotiating · Active · Restricted · Expired · Terminated
Submission status (StatutorySubmission): Draft · InternalReview · Ready ·
Submitted · Accepted · QueryRaised · Rejected · ResubmissionRequired · Closed
Requirement validation: NotChecked · Pass · Warning · Fail · NotApplicable
Correspondence — direction: Inbound · Outbound; response status: None ·
Required · Preparing · Sent · Overdue · Closed
Variation / exemption status: Draft · Submitted · UnderReview · Approved ·
PartApproved · Rejected · Withdrawn
Renewal status: Planned · Preparing · Submitted · UnderReview · Approved ·
Conditional · Rejected · Withdrawn
Relinquishment status: Planned · Preparing · Submitted · Accepted · Rejected ·
Completed
Compliance-risk — residual rating: Low · Moderate · High · Critical; trend:
Improving · Stable · Worsening; status: Open · Monitoring · Mitigating ·
Accepted · Closed
Decision type: Submit · Renew · Vary · Exempt · Relinquish · Escalate ·
AcceptRisk · Remediate
Rules of Thumb
- The tenement is the hub. Almost everything — obligations, commitments,
permits, submissions, applications, risks, evidence, decisions — is scoped to a
specific
Tenement. Start from the licence, not the project. - Required, eligible actual, forecast, shortfall and exemption are five
different numbers. They live on
ExpenditureObligationand answer different questions;shortfall = required − eligible actual − exemption − carry-forward. TheEligibleExpenditureline items are the audit trail beneath them. - A commitment is measured against actuals, not asserted.
WorkProgrammeCommitmentstores committed and actual quantity/expenditure and a computed variance.WPC-Y3-DRILLat −1450 m is why the year isAtRisk. - A submission is only as good as its requirements.
SubmissionRequirementline items carry thePass/Warning/Failvalidation; a singleWarning(the apportionment query) is what putSUB-AR-Y2intoQueryRaised. - An at-risk obligation drives an application. The realistic path is
shortfall → risk → decision → variation + exemption, and the demo takes it:
EXPO-Y3→CR-01→DEC-EL-02→EXM-01. - Evidence is linked to obligations explicitly.
ObligationEvidencesays whether anEvidenceItemSupports,Completes, isPartialto or evenContradictsaStatutoryObligation— aMETclaim with no evidence link behind it is incomplete. - The snapshot is a stored roll-up, not a live calculation.
ComplianceSnapshotcounts and the coverage percent are seeded values; in Phase 2 the business rules compute them. Read the rows beneath before trusting the totals.